Planning condition discharge in England and Wales

Contents

[edit] Introduction

Planning condition discharge is the formal process by which a developer satisfies conditions attached to a planning permission before or during construction. Local planning authorities (LPAs) in England and Wales routinely attach conditions to planning permissions requiring specific matters to be approved prior to commencement, prior to occupation, or during the construction phase.

[edit] What is planning condition discharge?

When a planning permission is granted, it is often subject to conditions that must be satisfied before development can begin or be completed. Discharging a planning condition means formally applying to the LPA to confirm that the requirements of that condition have been met.

Failure to discharge conditions prior to commencement — where conditions are described as 'pre-commencement' — can render development unlawful, even if planning permission has been granted.

[edit] Types of planning conditions

Planning conditions generally fall into the following categories:

[edit] The discharge process

To discharge a planning condition, the applicant must submit a formal application to the relevant LPA using the Planning Portal. The application must include:

Common technical reports submitted as part of discharge applications include:

LPAs are required to consult relevant statutory consultees before issuing a decision. The quality and completeness of technical submissions significantly affects the speed of approval.

[edit] Timescales and fees

Under the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations, the standard fee for a householder discharge application is £34 per condition. For other categories of development, the fee is £116 per request (which may cover multiple conditions).

LPAs have a statutory target of 8 weeks to determine discharge of condition applications. In practice, performance varies significantly between authorities. Applications with incomplete or insufficient technical evidence are frequently returned or subject to extended negotiation.

[edit] Common reasons for refusal or delay

Discharge applications are commonly delayed or refused for the following reasons:

Applicants can reduce delays by ensuring technical reports are prepared by qualified specialists with experience of local authority requirements, and by pre-application engagement with the LPA where conditions are complex.

[edit] Related articles on Designing Buildings

Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again